Complete kitchen and servery redesign incorporating a new central cooking area, mechanical extraction with gas interlock, bespoke stainless steel fabrication, and a new heavy-duty servery counter with Ceran worktops, heated gantries and grab-and-go units. Appointed via GNAS facilities management. Completed on time and on budget.
The Waltons Academy, Grantham, forms part of a diverse academy group served by their facilities management partners GNAS. Castle Catering Engineers were appointed through competitive tender to redesign and update the school's existing catering facilities, encompassing the main kitchen and servery area, with the objective of creating a more efficient, workable environment for kitchen staff and increasing food production capacity to meet growing pupil numbers.
A new central cooking area was introduced as the heart of the kitchen redesign, housing the gas and electric cooking equipment in a logical, ergonomic configuration that maximises workflow for the catering team. A new efficient mechanical extraction system was designed and installed incorporating a gas interlocking system and mechanical air-in to meet current ventilation regulations and BS6173 compliance requirements. All gas works were carried out by Gas Safe registered engineers (Licence 597490) with CP42 certification issued on completion.
Works also included an enlarged dishwash area, new bespoke stainless steel sinks and preparation benches, and a new heavy-duty main servery counter designed specifically to serve the academy's increasing daily pupil numbers efficiently. The servery was specified with built-in Ceran worktops, heated gantries, hot cupboards, and refrigerated and heated grab-and-go units to accelerate service throughput during peak periods.
Equipment from Rational, Hobart and Blue Seal was supplied and installed. CCE's in-house team of engineers managed the full installation, commissioning and staff training, completing the project on time and on budget.
| Client | The Waltons Academy, Grantham |
| Location | Grantham, Lincolnshire |
| Appointed by | GNAS Facilities Management |
| Scope | Complete kitchen and servery redesign and installation |
| Gas Safe | Licence 597490 |
| Key works | New central cooking area, extraction, gas interlock, bespoke SS fabrication, servery counter |
| Equipment | Rational, Hobart, Blue Seal |
| Servery | Ceran worktops, heated gantries, hot cupboards, grab-and-go units |
| Delivery | On time and on budget |
| Certification | CP42 issued on completion |





Castle Catering Engineers were appointed through competitive tender by GNAS, the facilities management partner for the academy group. This is a common route to CCE for academy trust and education sector kitchen projects across the East Midlands and Lincolnshire.
Complete kitchen and servery redesign: new central cooking area, mechanical extraction with gas interlock and mechanical air-in, enlarged dishwash area, bespoke stainless steel sinks and benches, and a new heavy-duty servery counter with Ceran worktops, heated gantries, hot cupboards and grab-and-go units. Rational, Hobart and Blue Seal equipment throughout.
Yes. CCE in-house engineers managed the full installation, commissioning and staff training across all new equipment, ensuring the kitchen team were confident and fully operational before handover.
Yes. CCE regularly works with academy trusts, MATs and facilities management partners across Nottinghamshire, Lincolnshire and the wider East Midlands. Contact us to discuss your education catering project.
Appointed by GNAS on behalf of The Waltons Academy. DBS Enhanced approved, Gas Safe (Licence 597490), CSCS members. Free site survey across the East Midlands and Lincolnshire.